INTERACTIVE · CYFUN IMPLEMENTATION PLANNER
How long does a CyFun programme take for you?
Pick a start month, an assurance level and your available capacity. The schedule, milestones and end date follow. This is a generic planning model, not a quote and not a conformity statement.
When do you confirm scope and begin?
The level follows from a risk assessment, not from your size.
How much internal traction is there?
Roadmap
Each bar is a work package. The diamond marks a milestone.
| 2026 | 2027 | ||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Sep | Oct | Nov | Dec | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | ||
| GOVERN | Scope, context and level determination | ||||||||||||||||
| Baseline assessment and gap analysis | |||||||||||||||||
| Policy and governance structure | |||||||||||||||||
| Risk methodology and risk register | |||||||||||||||||
| Training and awareness | |||||||||||||||||
| Performance measurement and management review | |||||||||||||||||
| IDENTIFY | Asset and data inventory | ||||||||||||||||
| Risk assessment and statement of applicability | |||||||||||||||||
| Supply chain and supplier controls | |||||||||||||||||
| PROTECT | Documentation set per clauses 4-10 | ||||||||||||||||
| Access and identity management | |||||||||||||||||
| Patch and configuration management | |||||||||||||||||
| Data security and classification | |||||||||||||||||
| Network and infrastructure resilience | |||||||||||||||||
| DETECT | Logging and central monitoring | ||||||||||||||||
| Detection processes and anomaly detection | |||||||||||||||||
| RESPOND | Incident response and notification | ||||||||||||||||
| Exercise, evaluation and improvement | |||||||||||||||||
| RECOVER | Continuity and recovery planning | ||||||||||||||||
| Recovery test and communication | |||||||||||||||||
| CLOSING | Internal audit | ||||||||||||||||
| Verification by accredited body | |||||||||||||||||
| ◆ | ◆ | ◆ | ◆ | ◆ | |||||||||||||
Show as table
| Function | Work package | Start | End | Months |
|---|---|---|---|---|
| GOVERN | Scope, context and level determination | Sep 2026 | Oct 2026 | 2 |
| GOVERN | Baseline assessment and gap analysis | Oct 2026 | Dec 2026 | 3 |
| GOVERN | Policy and governance structure | Nov 2026 | Feb 2027 | 4 |
| GOVERN | Risk methodology and risk register | Dec 2026 | Mar 2027 | 4 |
| GOVERN | Training and awareness | Feb 2027 | Jun 2027 | 5 |
| GOVERN | Performance measurement and management review | Jun 2027 | Nov 2027 | 6 |
| IDENTIFY | Asset and data inventory | Dec 2026 | Apr 2027 | 5 |
| IDENTIFY | Risk assessment and statement of applicability | Feb 2027 | May 2027 | 4 |
| IDENTIFY | Supply chain and supplier controls | Mar 2027 | Jul 2027 | 5 |
| PROTECT | Documentation set per clauses 4-10 | Nov 2026 | Mar 2027 | 5 |
| PROTECT | Access and identity management | Feb 2027 | Jul 2027 | 6 |
| PROTECT | Patch and configuration management | Mar 2027 | Jul 2027 | 5 |
| PROTECT | Data security and classification | Apr 2027 | Aug 2027 | 5 |
| PROTECT | Network and infrastructure resilience | May 2027 | Sep 2027 | 5 |
| DETECT | Logging and central monitoring | May 2027 | Sep 2027 | 5 |
| DETECT | Detection processes and anomaly detection | Jul 2027 | Oct 2027 | 4 |
| RESPOND | Incident response and notification | Apr 2027 | Aug 2027 | 5 |
| RESPOND | Exercise, evaluation and improvement | Sep 2027 | Nov 2027 | 3 |
| RECOVER | Continuity and recovery planning | Jun 2027 | Oct 2027 | 5 |
| RECOVER | Recovery test and communication | Oct 2027 | Dec 2027 | 3 |
| CLOSING | Internal audit | Oct 2027 | Nov 2027 | 2 |
| CLOSING | Verification by accredited body | Nov 2027 | Dec 2027 | 2 |
Milestones and exit criteria
A date only becomes a milestone once the decisive evidence exists.
| Milestone | Date | Minimum exit criterion |
|---|---|---|
| Baseline assessment delivered | Dec 2026 | Scope and entity type confirmed; applicability per requirement; current asset and supplier baseline; findings with owner and deadline. |
| Documentation set ready | Mar 2027 | Risk methodology, control register and core policies approved; design test performed; dependencies assigned. |
| Internal audit completed | Nov 2027 | Operating-effectiveness test passed on core controls; evidence assessed as adequate; open actions within deadline. |
| Verification by accredited body | Dec 2027 | Complete file submitted; independent validation concluded. |
Curious what is already in place at your organisation?
A baseline assessment turns this model into a plan. Call or mail to scope it.
CyFun® and the CyberFundamentals Framework are developed and published by the Centre for Cybersecurity Belgium (CCB). RGI bv is not affiliated with the CCB and does not act on its behalf. Requirement texts come from the official CyFun® 2025 publication; the reuse analysis, the clause relations and the planning model are an RGI bv analysis. ISO standards are referenced by clause and control number only; standard texts are copyrighted and are not reproduced here.